2019/061: Regarding the compliance of a surface water drainage connection

Abbreviation
2019/061
Valid from
4/12/2019

Information provider
Ministry of Business, Innovation and Employment
Author
Ministry of Business, Innovation and Employment
Information type
Determination
Format
PDF

Description

This determination considers whether a surface water drain complies with Building Code Clause E1 Surface water: the drain collects water from a roof and is connected to a kerb sump and not directly to a surface water drain.

The authority considers the connection to the sump was contrary to the means of compliance stated in the building consent, being the Acceptable Solution for Clause E1, and that approval should be sought for the work as a minor variation to the consent.

For assistance with locating previous versions, please contact the information provider.
View on Information Provider website Download this resource (PDF, 1.4MB)
For assistance with locating previous versions, please contact the information provider.
This resource is not cited by any other resources.

2019/061: Regarding the compliance of a surface water drainage connection

This document is not CITED BY any other resources:

2019/061: Regarding the compliance of a surface water drainage connection

Description

This determination considers whether a surface water drain complies with Building Code Clause E1 Surface water: the drain collects water from a roof and is connected to a kerb sump and not directly to a surface water drain.

The authority considers the connection to the sump was contrary to the means of compliance stated in the building consent, being the Acceptable Solution for Clause E1, and that approval should be sought for the work as a minor variation to the consent.

View on Information Provider website Download this resource (PDF, 1.4MB)
2019/061: Regarding the compliance of a surface water drainage connection
Description

This determination considers whether a surface water drain complies with Building Code Clause E1 Surface water: the drain collects water from a roof and is connected to a kerb sump and not directly to a surface water drain.

The authority considers the connection to the sump was contrary to the means of compliance stated in the building consent, being the Acceptable Solution for Clause E1, and that approval should be sought for the work as a minor variation to the consent.

View on Information Provider website Download this resource (PDF, 1.4MB)
This resource does not cite any other resources.