2015/021: Regarding the refusal to issue an exemption under Schedule 1(2) for plumbing and drainage work

Abbreviation
2015/021
Valid from
11/05/2015

Information provider
Ministry of Business, Innovation and Employment,
Information type
Determination,
Format
PDF,

Description

This determination arises from a dispute between the parties as to whether building work to install sanitary plumbing requires building consent or is exempt under Schedule 1(2).

The matter to be determined is therefore whether the authority correctly exercised its powers in refusing to grant an exemption under Schedule 1(2) for installation of sanitary plumbing. In making this decision I have considered whether the proposed building work can be considered exempt under Schedule 1(2).

For assistance with locating previous versions, please contact the information provider.
View on Information Provider website Download this resource (PDF, 114KB)
For assistance with locating previous versions, please contact the information provider.
This resource is not cited by any other resources.

2015/021: Regarding the refusal to issue an exemption under Schedule 1(2) for plumbing and drainage work

This document is not CITED BY any other resources:

2015/021: Regarding the refusal to issue an exemption under Schedule 1(2) for plumbing and drainage work

Description

This determination arises from a dispute between the parties as to whether building work to install sanitary plumbing requires building consent or is exempt under Schedule 1(2).

The matter to be determined is therefore whether the authority correctly exercised its powers in refusing to grant an exemption under Schedule 1(2) for installation of sanitary plumbing. In making this decision I have considered whether the proposed building work can be considered exempt under Schedule 1(2).

View on Information Provider website Download this resource (PDF, 114KB)
2015/021: Regarding the refusal to issue an exemption under Schedule 1(2) for plumbing and drainage work
Description

This determination arises from a dispute between the parties as to whether building work to install sanitary plumbing requires building consent or is exempt under Schedule 1(2).

The matter to be determined is therefore whether the authority correctly exercised its powers in refusing to grant an exemption under Schedule 1(2) for installation of sanitary plumbing. In making this decision I have considered whether the proposed building work can be considered exempt under Schedule 1(2).

View on Information Provider website Download this resource (PDF, 114KB)