2014/031: Regarding the authority's refusal to issue an exemption under Schedule 1(k) for a proposed greenhouse

Abbreviation
2014/031
Valid from
22/07/2014

Information provider
Ministry of Business, Innovation and Employment
Information type
Determination
Format
PDF

Description

This determination arose from the authority's decision to refuse an exemption from the requirement to obtain a building consent for the erection of a greenhouse.

The authority stated they were satisfied that the proposed building work did not meet the criteria specified in Schedule 1(k) of the Act.

The matter to be determined was therefore whether the authority correctly exercised its powers in refusing to issue an exemption under Schedule 1(k) of the Act.

For assistance with locating previous versions, please contact the information provider.
View on Information Provider website Download this resource (PDF, 315KB)
For assistance with locating previous versions, please contact the information provider.
This resource is not cited by any other resources.

2014/031: Regarding the authority's refusal to issue an exemption under Schedule 1(k) for a proposed greenhouse

This document is not CITED BY any other resources:

2014/031: Regarding the authority's refusal to issue an exemption under Schedule 1(k) for a proposed greenhouse

Description

This determination arose from the authority's decision to refuse an exemption from the requirement to obtain a building consent for the erection of a greenhouse.

The authority stated they were satisfied that the proposed building work did not meet the criteria specified in Schedule 1(k) of the Act.

The matter to be determined was therefore whether the authority correctly exercised its powers in refusing to issue an exemption under Schedule 1(k) of the Act.

View on Information Provider website Download this resource (PDF, 315KB)
2014/031: Regarding the authority's refusal to issue an exemption under Schedule 1(k) for a proposed greenhouse
Description

This determination arose from the authority's decision to refuse an exemption from the requirement to obtain a building consent for the erection of a greenhouse.

The authority stated they were satisfied that the proposed building work did not meet the criteria specified in Schedule 1(k) of the Act.

The matter to be determined was therefore whether the authority correctly exercised its powers in refusing to issue an exemption under Schedule 1(k) of the Act.

View on Information Provider website Download this resource (PDF, 315KB)
This resource does not cite any other resources.

2014/031: Regarding the authority's refusal to issue an exemption under Schedule 1(k) for a proposed greenhouse

This resource does not CITE any other resources.
Feedback