The BRANZ helpline has been asked recently about how best to detail the tricky junction between the top edge of a monopitch roof and an adjacent wall above. Here is one suggestion.

This continues the Build series on roof-to-wall junction details not included in Acceptable Solution E2/AS1 to the New Zealand Building Code clause E2 External moisture.

 

For assistance with locating previous versions, please contact the information provider.
Download this resource (PDF)
For assistance with locating previous versions, please contact the information provider.
This resource is not cited by any other resources.

Roof-to-wall junction detail - Build 165(2018)

This document is not CITED BY any other resources:

Roof-to-wall junction detail - Build 165(2018)

Description

The BRANZ helpline has been asked recently about how best to detail the tricky junction between the top edge of a monopitch roof and an adjacent wall above. Here is one suggestion.

This continues the Build series on roof-to-wall junction details not included in Acceptable Solution E2/AS1 to the New Zealand Building Code clause E2 External moisture.

 

Download this resource (PDF)
Roof-to-wall junction detail - Build 165(2018)
Description

The BRANZ helpline has been asked recently about how best to detail the tricky junction between the top edge of a monopitch roof and an adjacent wall above. Here is one suggestion.

This continues the Build series on roof-to-wall junction details not included in Acceptable Solution E2/AS1 to the New Zealand Building Code clause E2 External moisture.

 

Download this resource (PDF)
This resource does not cite any other resources.

Roof-to-wall junction detail - Build 165(2018)

This resource does not CITE any other resources.
Feedback