2020/030: Regarding the purported refusal to grant a building consent because of a dispute about the importance level of the building

Abbreviation
2020/030
Valid from
17/11/2020

Information provider
Ministry of Business, Innovation and Employment
Information type
Determination
Format
PDF

Description

This determination considers the authority's purported refusal to grant a building consent for proposed building work because the authority did not agree with the importance level proposed by the structural engineer.

The determination discusses whether the subject building should be classified as Importance Level 2 or Importance Level 3 as set out in Australian/New Zealand Standard 1170.0. This standard is referenced by Verification Method B1/VM1, which is a means of compliance with Building Code Clause B1 Structure.

For assistance with locating previous versions, please contact the information provider.
View on Information Provider website Download this resource (PDF, 281KB)
For assistance with locating previous versions, please contact the information provider.
This resource is not cited by any other resources.

2020/030: Regarding the purported refusal to grant a building consent because of a dispute about the importance level of the building

This document is not CITED BY any other resources:

2020/030: Regarding the purported refusal to grant a building consent because of a dispute about the importance level of the building

Description

This determination considers the authority's purported refusal to grant a building consent for proposed building work because the authority did not agree with the importance level proposed by the structural engineer.

The determination discusses whether the subject building should be classified as Importance Level 2 or Importance Level 3 as set out in Australian/New Zealand Standard 1170.0. This standard is referenced by Verification Method B1/VM1, which is a means of compliance with Building Code Clause B1 Structure.

View on Information Provider website Download this resource (PDF, 281KB)
2020/030: Regarding the purported refusal to grant a building consent because of a dispute about the importance level of the building
Description

This determination considers the authority's purported refusal to grant a building consent for proposed building work because the authority did not agree with the importance level proposed by the structural engineer.

The determination discusses whether the subject building should be classified as Importance Level 2 or Importance Level 3 as set out in Australian/New Zealand Standard 1170.0. This standard is referenced by Verification Method B1/VM1, which is a means of compliance with Building Code Clause B1 Structure.

View on Information Provider website Download this resource (PDF, 281KB)
This resource does not cite any other resources.

2020/030: Regarding the purported refusal to grant a building consent because of a dispute about the importance level of the building

This resource does not CITE any other resources.
Feedback