2012/040: Refusal to issue a code compliance certificate for a ten year-old house completed under the supervision of a building certifier

Abbreviation
2012/040
Valid from
25/05/2012

Information provider
Ministry of Business, Innovation and Employment
Information type
Determination
Format
PDF

Description

The matter to be determined is whether the authority correctly exercised its powers in respect of its refusal to issue a code compliance certificate. Subsequent to the completion of the building work remedial work was undertaken for which no consent was sought. Therefore in making my decision the following must be considered: 1-whether a building consent was required for the unconsented remedial work; 2-whether the consented building work complies with the relevant clauses of the Building Code; 3-whether the remedial building work complies with the relevant clauses of the Building Code; 4-whether a code compliance certificate, or some other certificate, is the most appropriate certificate to be issued in due course.

For assistance with locating previous versions, please contact the information provider.
View on Information Provider website Download this resource (PDF, 252KB)
For assistance with locating previous versions, please contact the information provider.
This resource is not cited by any other resources.

2012/040: Refusal to issue a code compliance certificate for a ten year-old house completed under the supervision of a building certifier

This document is not CITED BY any other resources:

2012/040: Refusal to issue a code compliance certificate for a ten year-old house completed under the supervision of a building certifier

Description

The matter to be determined is whether the authority correctly exercised its powers in respect of its refusal to issue a code compliance certificate. Subsequent to the completion of the building work remedial work was undertaken for which no consent was sought. Therefore in making my decision the following must be considered: 1-whether a building consent was required for the unconsented remedial work; 2-whether the consented building work complies with the relevant clauses of the Building Code; 3-whether the remedial building work complies with the relevant clauses of the Building Code; 4-whether a code compliance certificate, or some other certificate, is the most appropriate certificate to be issued in due course.

View on Information Provider website Download this resource (PDF, 252KB)
2012/040: Refusal to issue a code compliance certificate for a ten year-old house completed under the supervision of a building certifier
Description

The matter to be determined is whether the authority correctly exercised its powers in respect of its refusal to issue a code compliance certificate. Subsequent to the completion of the building work remedial work was undertaken for which no consent was sought. Therefore in making my decision the following must be considered: 1-whether a building consent was required for the unconsented remedial work; 2-whether the consented building work complies with the relevant clauses of the Building Code; 3-whether the remedial building work complies with the relevant clauses of the Building Code; 4-whether a code compliance certificate, or some other certificate, is the most appropriate certificate to be issued in due course.

View on Information Provider website Download this resource (PDF, 252KB)
This resource does not cite any other resources.

2012/040: Refusal to issue a code compliance certificate for a ten year-old house completed under the supervision of a building certifier

This resource does not CITE any other resources.
Feedback