Movement control joints in plastered finishes

Abbreviation
Movement control joints in plastered finishes - Issue 82
Valid from
1/02/2018

Information provider
Ministry of Business, Innovation and Employment
Information type
CodeWords article
Format
Website

Description

Work on a plaster-based cladding system is restricted building work (RBW), unless you are doing repairs, replacement or maintenance work under Schedule 1.

All RBW requires building consent and if you are doing the work you either need to hold an external plastering licence or be supervised by someone who does.

For assistance with locating previous versions, please contact the information provider.
View on Information Provider website
For assistance with locating previous versions, please contact the information provider.
This resource is not cited by any other resources.

Movement control joints in plastered finishes

This document is not CITED BY any other resources:

Movement control joints in plastered finishes

Description

Work on a plaster-based cladding system is restricted building work (RBW), unless you are doing repairs, replacement or maintenance work under Schedule 1.

All RBW requires building consent and if you are doing the work you either need to hold an external plastering licence or be supervised by someone who does.

View on Information Provider website
Movement control joints in plastered finishes
Description

Work on a plaster-based cladding system is restricted building work (RBW), unless you are doing repairs, replacement or maintenance work under Schedule 1.

All RBW requires building consent and if you are doing the work you either need to hold an external plastering licence or be supervised by someone who does.

View on Information Provider website