2018/043: Refusal to accept a building consent application for a new building

Abbreviation
2018/043
Valid from
7/09/2018

Information provider
Ministry of Business, Innovation and Employment
Information type
Determination
Format
PDF

Description

This determination considers the authority’s refusal to accept a building consent application. The determination considers whether sufficient information was provided to the authority as required by section 45 of the Building Act.

This determination arises from the authority's refusal to accept a building consent application, as the proposed building was outside the scope of the Acceptable Solution E2/AS1. The refusal arose because the authority was not satisfied it had enough information to accept the building consent application and was of the view the proposed building work would not comply with Clause E2 External moisture of the Building Code (First Sschedule, Building Regulations 1992) 

 

For assistance with locating previous versions, please contact the information provider.
View on Information Provider website Download this resource (PDF, 2.1MB)
For assistance with locating previous versions, please contact the information provider.
This resource is not cited by any other resources.

2018/043: Refusal to accept a building consent application for a new building

This document is not CITED BY any other resources:

2018/043: Refusal to accept a building consent application for a new building

Description

This determination considers the authority’s refusal to accept a building consent application. The determination considers whether sufficient information was provided to the authority as required by section 45 of the Building Act.

This determination arises from the authority's refusal to accept a building consent application, as the proposed building was outside the scope of the Acceptable Solution E2/AS1. The refusal arose because the authority was not satisfied it had enough information to accept the building consent application and was of the view the proposed building work would not comply with Clause E2 External moisture of the Building Code (First Sschedule, Building Regulations 1992) 

 

View on Information Provider website Download this resource (PDF, 2.1MB)
2018/043: Refusal to accept a building consent application for a new building
Description

This determination considers the authority’s refusal to accept a building consent application. The determination considers whether sufficient information was provided to the authority as required by section 45 of the Building Act.

This determination arises from the authority's refusal to accept a building consent application, as the proposed building was outside the scope of the Acceptable Solution E2/AS1. The refusal arose because the authority was not satisfied it had enough information to accept the building consent application and was of the view the proposed building work would not comply with Clause E2 External moisture of the Building Code (First Sschedule, Building Regulations 1992) 

 

View on Information Provider website Download this resource (PDF, 2.1MB)